Heerema Paint Shop

Client: Hartlepool Borough Council

Project Value: £438687.00 – Start Date: Sept 2013 Completed: December 2013

Brief Description of the Works

The contract covered a design and build project for Heerema Group with Hartlepool Borough Council as the CDM Co-ordinator and Tangent Construction as the Principal Contractor. It required ground investigation, a high specification concrete base on a large bed of steel reinforced mesh on 156 no 16m driven concrete piles – to withstand a 400 tonne static loading – and industrial cladding walls and roof.

The work was done within the site of the Heerema oil rig fabrication site, to rigorously specified health and safety standards and a tight construction programme. Tangent Construction managed the site and numerous specialist sub-contractors.